Valley Sanitary District Announces Sewer Project Schedule

INDIO, CA (December 2, 2016) – The Valley Sanitary District has released a schedule to perform sewer main construction work through the intersection of Requa Avenue and Jackson Street from Monday, December 5 and to Tuesday, December 13.  Construction work will be at night from 7:00 p.m. to 5:30 a.m., however, traffic control will be in place 24 hours a day. During this time, traffic will be reduced to one lane in each direction.  Access to businesses and residents will be maintained but residents and motorists are urged to use alternate routes since delays of up to 15 minutes and longer may be encountered. Access for emergency vehicles will be unaffected. This work is highly weather dependent and the schedule may need to be shifted if inclement weather occurs.

The construction schedule is as follows (all construction work will be at night from 7:00 p.m. to 5:30 a.m. unless otherwise noted):

Monday, December 5:

On Requa Ave. from Marshall St. to Jackson St.

Tuesday, December 6:

On Requa Ave. from east side of Jackson St. to the centerline of Jackson St.

Wednesday, December 7:

On Requa Ave. from centerline of Jackson St. to west side of Jackson St. A water main shutdown on Jackson St. will be part of this work.

Thursday, December 8:

On Requa Ave. from west side of Jackson St. to Fargo St.

Friday, December 9:

On Requa Ave. from east of Fargo St. up through Fargo St. A water main shutdown on Fargo St. will be part of this work.

Monday, December 12:

No construction work planned at this time but may be utilized if required.

Tuesday, December 13:

During the day, traffic control will be removed and traffic lanes returned to normal.

The Requa Sewer Project is the installation of a four-mile gravity flow sewer pipeline and related utility improvements from central Indio to VSD’s Water Reclamation Facility. Construction began in June 2016 at VSD’s treatment facility and will end in September 2017 at the intersection of Madison Street and Highway 111.  The cost of the project is $15 million and will add capacity for the future commercial growth and development of the City of Indio along the Highway 111 corridor.

 For more information, please call the Valley Sanitary District’s hotline at (760) 238-5413 from 7:30 a.m. to 5:00 p.m. or leave a message after hours.